The following information is for general information purposes. Please contact City Hall at
(615) 274-2922 for more information or if you have any questions.
City of Eagleville Permit Information Single Family Dwelling Permit
(SFD)
A sfd permit should have either a lot
and subdivision, and/or an physical address.
Tax Map and Parcel Number
Owner
Information and Phone Number (if available)
Development
Tax Receipt
SFD Permits can not be issued unless a development
tax receipt is submitted.
If a new mobile home or dwelling is replacing an existing dwelling,
and the existing dwelling has been demolished or removed a development tax exemption receipt can be issued and faxed to the
City of Eagleville. The person obtaining the permit or the city recorder can call Rutherford County Building Codes and request
an exemption receipt at the time the building permit is being obtained.
Any addition or accessory
structure containing a full kitchen, the full development tax must be paid before a building permit can be issued. (Any questions
pertaining to development tax can be referred to the Rutherford County Building Codes Department. 615-898-7734)
Development
Tax must be paid to the Rutherford County Building Codes Department.
The City of Eagleville
must ask the permit holder for the red stamped copy development tax receipt.
Who Can Pull
A Permit
Homeowner
State Licensed Contractor
(must have current copy of license on file)
Septic Approval
In order to obtain a building permit a septic permit must be submitted.
A
septic completion letter must be submitted to the building inspector before a final building inspection can be done.
Plans Review Required
A plans review is required
if a house has 5000 sq ft or more living space
A plans review is required if a house has a basement
A
plans review is required on all commercial projects, except a storage building
A
plans review takes 1-3 days for review, and must be done prior to issuance of a building permit or beginning construction.
A plans review charge will be assessed depending on the project and the extent of the plans review.Plans
must be reviewed at the Rutherford County Building Codes by either the Director or the Assistant Director.
All new commercial construction must go before the Eagleville Planning Commission.
A site plan, land survey and general business plan should be submitted to the Planning Commission and City Planner no later
than 14 business days prior to their next planned meeting to be considered at that meeting.